The five cost categories

Every multiplex development project carries the same five categories of cost. The relative weights shift by program, but the categories are always there.

1. Land acquisition

The cost to purchase the lot, plus the legal, due diligence, survey, and land transfer taxes attached. For most Toronto infill sites, this is the largest single line on the budget. It's also the only one that's largely set the moment you close.

2. Hard costs (construction)

Demolition of any existing structure, site preparation, excavation, foundation, framing, mechanical-electrical-plumbing rough-in, envelope, finishes, landscaping, and site servicing. This is what most people mean when they ask "what does it cost." It is also where the per-square-foot question gets asked and where it makes the least sense — see below.

3. Soft costs

Architectural and structural design, mechanical and electrical engineering, geotechnical, hydrogeological if needed, BCIN/legal, City of Toronto development charges and parkland dedication levies, building permit fees, insurance during construction, surveying and inspections. Soft costs vary widely by project and permitting path — an as-of-right build carries fewer of them than one going through approvals — so there's no single percentage you can pencil in. Keeping them down is something we work at deliberately on every file.

4. Financing

Construction-loan interest, lender fees, mortgage broker commissions, and the cost of the equity layer. Carrying cost is a function of how long the project takes — every month of delay compounds. The difference between an as-of-right project and one held up at a Committee of Adjustment is measured here.

5. Contingency

The honest acknowledgement that something will go wrong. We carry 5-10% on hard costs as a starting point, more on heavier scopes (deep excavation, heritage buildings, party walls). The unspent contingency at the end of a project is a sign of good planning, not over-budgeting.

Why "cost per square foot" is the wrong question

Almost every conversation about construction cost starts with PSF. We understand why — it's a single number that's easy to remember and easy to compare. But for this category of building, it's misleading more often than it's useful.

Here's why:

When someone publishes a PSF figure for "Toronto multiplex construction," they've averaged across all of these dimensions. The number isn't wrong; it just isn't a planning tool.

Better questions to ask

The questions we'd suggest replacing "what's the PSF?" with:

"What does it cost to deliver an unleveraged unit?"

Take total project cost (land + hard + soft + financing + contingency, ignoring leverage), divide by the unit count. This is the all-in delivered cost per rental door. It's the right input for thinking about whether a building program makes economic sense at projected rents and cap rates.

"What's the marginal cost of the next unit?"

Going from a fourplex to a sixplex on the same lot adds two more units inside roughly the same envelope. The marginal cost is much less than the average cost — most of the structure, foundation, and roof are already there. This is the right framing for deciding whether to push density.

"How much of this is fixed vs. variable to my decisions?"

Land cost is fixed. Development charges are largely fixed by unit count. Excavation depth and parking strategy are decisions you can make. Finish package is entirely a decision. Separating the levers you can pull from the ones you can't is more useful than a PSF average.

The variables that move cost the most

In our experience, three line items account for the majority of cost variation between otherwise-similar Toronto multiplex projects:

Excavation depth. A walkout basement on a sloped lot adds units cheaply. A deep dig on a flat lot adds units expensively. Below-grade construction also brings hydrogeological costs, shoring, dewatering, and waterproofing — all of which scale faster than above-grade construction.

Finishes. The single largest controllable variable. The same floor plan with two different finish packages can land a long way apart on hard costs. The right finish level is the one that matches the rents in the neighbourhood — over-finishing for the market is the most common cost mistake we see.

Parking. Above-grade surface parking is essentially free. Below-grade structured parking is among the most expensive things you can build. In neighbourhoods where the bylaw still requires parking, this is a real budget question; in neighbourhoods where parking minimums have been reduced or eliminated, you can often build no parking at all and lose nothing in lease-up.

What a decade of building has taught us

A few patterns from our delivered and in-construction projects:

Where we actually save you money: the approvals

Here's the part most cost conversations miss. The single biggest lever on a Toronto infill project isn't the finish package or the foundation — it's how many rentable square feet the City lets you build on the lot you already own. Two operators can buy the identical lot; the one whose team genuinely understands what that lot can support — and how to design and approve to it — ends up with a fundamentally better asset, at almost the same land and soft cost.

That is our core competency. We are not a repeatable-template builder chasing volume — we are the team that pushes the zoning envelope, through the Committee of Adjustment, rezonings, and the new Major Streets allowances, to extract the maximum a site can carry. We have one of the strongest approvals track records of anyone doing this work in Toronto, and it's what we're known for. Pair that with a trade-and-consultant network built over a decade that keeps construction costs among the lowest in the market, and the math compounds in the same direction every time: more building, more doors, a lower cost per unit, and a project de-risked because it isn't living on the margin.

How we'd answer your "what does it cost" question

If you bring us a site, the conversation we want to have isn't "what's the PSF on a Toronto sixplex." It's:

That's a five-question conversation, not a one-number answer. It's also the only conversation that produces a budget you can actually build to.

For where we focus, see large multiplexes (with fourplexes and sixplexes for smaller schemes). For how we run a project end-to-end — pushing the approvals and managing the build — see development management and construction management.

Have a site and a number in your head? We'll tell you whether it's the right number.

Get in touch

Related reading